Construction Updates

Upcoming Construction Activities

Date

November 30, 2021

Location

500 El Camino Real, Menlo Park

El Camino Real (ECR) Lane Closures and Night Work

  • New utilities installations require temporary closures of two northbound traffic lanes and sidewalk on ECR through November. These activities take place on weekdays from 9:00 A.M.–3:00 P.M.
  • Night work will be required November 29–December 3, 9:00 P.M. – 6:00 A.M. Caltrans policy mandates that multiple lane closures only take place at night to avoid traffic impacts.
  • ECR work will occur intermittently and follow this approximate construction schedule:
    • Sanitary Sewer Line Installation: Completed
    • Hydrant Installations: Completed
    • Storm Line Installation: September–November 2021
    • Water Line Installation: September–November 2021
    • Pipe Work and Testing: November 29–December 3
    • Roadway Repaving: January–February 2022

Other Offsite Impacts

  • Sidewalk and street improvement work continues.

Office Buildings

Building 1

  • Exterior waterproofing and stucco installation continue through December 3rd.
  • Roof tile and membrane installations continue.
  • Interior work on the core revisions and additional elevators continues.

Building 2

  • Stairway handrails and cable rails installation is ongoing.
  • Exterior and interior painting continues.
  • Waterproofing of the ground-level concrete deck and balconies continues. Concrete pours for planter boxes, sidewalks, curbs and gutter near the train tracks are ongoing.
  • Parking lot and access road grading continue.

Building 3

  • Parking lot and access road grading continues.

Residential Buildings & Pool

  • Exterior sheathing, roofing, detailing, and inspections continue.
  • Solar panel installation continues.
  • Exterior painting for Building C is nearing completion; electrical installations will follow.
  • Wood framing is nearing completion for Building A.
  • Interior construction and inspections for Building A, B and C continue.
  • Siding, weatherproofing, and painting on Building B exterior continues.
  • Bridge construction and waterproofing continues at Buildings A, B and C.
  • Balcony railing work continues.
  • Forming of the pool continues.

Garage

  • Electrical room construction for Building A continues through November.
  • Insulation, shoring, steel, and temporary supporting structure erection is ongoing.
  • HVAC and electrical inspections continue.
  • Seismic bracing continues.

Stormwater Drainage System

  • Water tie-in is set to begin following the completion of water line installations for Office Buildings 2 and 3.
  • Bioswale and onsite landscaping will follow.

 

Updates Archive

PLEASE NOTE:  Sitewide work restarted under appropriate COVID-19 protocols for construction projects, as recommended by the Centers for Disease Control and Prevention and local health officials. Our commitment to the community continues, as we collect community feedback, share information, and mitigate as many impacts as possible to ensure the safety of construction workers and community members.


General Construction Information

Construction site access is via El Camino Real at Cambridge Avenue, Middle Avenue and Partridge Avenue.

Roadway flaggers will be on duty as needed to direct trucks and equipment entering and leaving the construction site.

There is noise and dust associated with construction operations. Noise is mitigated as much as possible; however, intermittent noise disruptions can occur. Construction requirements will be met per code. Dust control operations, via water spray, coincide with these operations.


Construction Hours

Construction hours are compliant with the City of Menlo Park’s Construction Policy.

Please note that there may be instances where Project construction activities take place during the evening and/or weekends when deemed necessary to reduce construction impacts on traffic along El Camino Real. This will be done with the required necessary approval from the City of Menlo Park.