Construction Updates

Upcoming Construction Activities

Date

October 12, 2021

Location

500 El Camino Real, Menlo Park

El Camino Real (ECR) Lane Closures and Night Work

  • New storm and water line installation will require temporary closures of two northbound traffic lanes and sidewalk on ECR.
  • Day work will take place during weekdays through October.
  • Night work will be required September 20–October 15, Sunday–Thursday, 9:00 P.M.–1:00 P.M. Caltrans policy mandates that multiple lane closures only take place at night to avoid traffic impacts.
  • ECR work will occur intermittently and follow this approximate construction schedule:
    • Sanitary Sewer Line Installation: Completed
    • Hydrant Installations: October 18–22, 25–29
    • Storm Line Installation: September–October 2021
    • Water Line Installation: September–November 2021
    • Roadway Repaving: January–February 2022

Other Offsite Impacts

  • Sidewalk and street improvement work continues.

Office Buildings

Building 1

  • Exterior waterproofing and stucco installation continue through mid-November.
  • Roof tile and membrane installations have begun.

Building 2

  • Stairway handrails and cable rails installation is ongoing.
  • Stucco work, roofing, and trellis installations have been completed.
  • Exterior painting continues.
  • Waterproofing of the ground-level concrete deck and balconies continues. Concrete pours for planter boxes, sidewalks, and curbs near the train tracks will follow.

Building 3

  • Restroom accessories installation continues.
  • Construction of trash enclosure foundations has begun.

Residential Buildings & Pool

  • Exterior sheathing, roofing, detailing, and inspections continue.
  • Solar panel installation continues.
  • Wood framing is nearing completion for Building A.
  • Interior construction and inspections for Building A, B and C continues, including elevator installations.
  • Siding, weatherproofing, and painting on Building B exterior continues.
  • Building A scaffold to remain until exterior of the building is completed.
  • Bridge construction and waterproofing continues at Buildings A, B and C.
  • Balcony railing work continues.
  • Pool inspections are expected to complete by end of October, plumbing installation will follow.

Garage

  • Electrical room construction for Building A is anticipated to complete by late October.
  • Insulation, shoring, steel, and temporary supporting structure erection is ongoing.
  • Sprinkler system inspections is expected to complete by early November.
  • HVAC and electrical inspections continue.
  • Seismic bracing continues.

Stormwater Drainage System

  • Water tie-in is set to begin following the completion of water line installations for Office Buildings 2 and 3.
  • Bioswale and onsite landscaping will follow.

 

Updates Archive

PLEASE NOTE:  Sitewide work restarted under appropriate COVID-19 protocols for construction projects, as recommended by the Centers for Disease Control and Prevention and local health officials. Our commitment to the community continues, as we collect community feedback, share information, and mitigate as many impacts as possible to ensure the safety of construction workers and community members.


General Construction Information

Construction site access is via El Camino Real at Cambridge Avenue, Middle Avenue and Partridge Avenue.

Roadway flaggers will be on duty as needed to direct trucks and equipment entering and leaving the construction site.

There is noise and dust associated with construction operations. Noise is mitigated as much as possible; however, intermittent noise disruptions can occur. Construction requirements will be met per code. Dust control operations, via water spray, coincide with these operations.


Construction Hours

Construction hours are compliant with the City of Menlo Park’s Construction Policy.

Please note that there may be instances where Project construction activities take place during the evening and/or weekends when deemed necessary to reduce construction impacts on traffic along El Camino Real. This will be done with the required necessary approval from the City of Menlo Park.